Hello sir, I want to know information about the treatment plant that is continue in a collage so you give me detail about the Sewage treatment plant and you also tell me what proposal for the continue this treatment in a collage.
|
#2
| ||||
| ||||
![]()
You want to know information about the treatment plant for the collage so I m am listing here some figure that will suggest you some information about collage: 500.000 person equivalent 7.813 – 12.500 m³/h Effluent parameters at water temperatures of 12°C COD ≤ 75 mg/l BOD5 ≤ 15 mg/l NH4-N ≤ 10 mg/l Ptot ≤ 1 mg/l European gross cost estimate 19,800,000 EUR Optional sewage sludge combustion plant 6,800,000 EUR Operating costs Electricity: 55.000 kWh/d Amount of surplus sludge: 137 t/d