You want to see present status of Delhi Metro Rail Corporation Phase I & II Network Project so here is its status:

Line 1 (Dilshad Garden - Rithala) - Red Line

Line - 1 (Dilshad Garden - Rithala) was made operational for commercial services in four stages:

Shahdara - Tis Hazari : with effect from 25th December, 2002 (Phase - I).

Tis Hazari - Inderlok : with effect from 4th October, 2003 (Phase - I).

Inderlok - Rithala : with effect from 1st April, 2004 (Phase - I).

Dilshad Garden - Shahdara : with effect from 3rd June 2008 (Phase - II).



Line 2 ( HUDA City Centre - Jahangirpuri) - Yellow Line

Line - 2 (HUDA City Centre - Jahangirpuri) was made operational for commercial services in five stages:

Vishwavidyalaya - Kashmere Gate : with effect from 20th December, 2004 (Phase - I).

Kashmere Gate - Central Secretariat : with effect from 3rd July, 2005 (Phase - I).

Vishwavidyalaya - Jahangirpuri : with effect from 3rd February 2009 (Phase - II).

HUDA City Centre - Qutab Minar : with effect from 21st June 2010 (Phase - II).

Central Secretariat - Qutab Minar : with effect from 3rd September 2010 (Phase - II).



Line 3 (Dwarka Sector 21 - Noida City Centre) - Blue Line

Line - 3 (Dwarka Sector 21 - Noida City Centre) was made operational for commercial services in six stages:

Barakhamba - Dwarka : with effect from 31st December 2005 (Phase - I)

Dwarka - Dwarka Sector 9 : with effect from 1st April 2006 (Phase - I).

Barakhamba - Indraprastha : with effect from 11th November 2006 (Phase - I).

Indraprastha - Yamuna Bank : with effect from 10th May 2009 (Phase - II).

Yamuna Bank - Noida City Centre : with effect from 13th November 2009 (Phase - II).

Dwarka sector 9 - Dwarka Sector 21 : with effect from 30th October 2010 (Phase - II).

Line 4 (Yamuna Bank - Anand Vihar ISBT) - Blue Line

Yamuna Bank - Anand Vihar ISBT : with effect from 6th January 2010 (Phase - II).

Line 5 (Inderlok - Mundka) - Green Line

Inderlok - Mundka : with effect from 2nd April 2010 (Phase - II).

Line 6 (Central Secretariat - Badarpur) - Violet Line

Central Secretariat - Sarita Vihar : with effect from 3rd October 2010 (Phase - II).

Sarita Vihar to Badarpur : With effect from 14th January 2011 (phase-II).

Airport Metro Express Line

New Delhi - IGI Airport(T-3)- Dwarka Sector-21 With Effect from 23rd February (Phase - II).
__________________
https://t.me/pump_upp
Reply With Quote
  #3  
Old June 8th, 2020, 10:46 AM
Unregistered
Guest
 
Default Re: DMRC India Delhi

I have some work in Delhi Metro Rail Corporation Limited (DMRC). Will you provide DMRC India Delhi Map so that I get all routes details also provide List of consulting projects?
Reply With Quote
  #4  
Old June 8th, 2020, 10:47 AM
Super Moderator
 
Join Date: Jun 2013
Default Re: DMRC India Delhi

The Delhi Metro has been instrumental in ushering in a new era in the sphere of mass urban transportation in India.

The Delhi Metro Rail Corporation Limited (DMRC) was registered on 3rd May 1995 under the Companies Act, 1956 with equal equity participation of the Government of the National Capital Territory of Delhi (GNCTD) and the Central Government to implement the dream of construction and operation of a world- class Mass Rapid Transport System (MRTS).

Below I am providing you the DMRC India Delhi Map:



List of consulting projects:

Sl. No Name of the Study / DPR Corridor Client Organisation
1 Badarpur - Faridabad Extension Badarpur to YMCA Chowk Govt. of Haryana
2 Mundka - Bahdurgarh Corridor Mundka- Bahdurgarh Govt. of Haryana
3 NOIDA Extension of Delhi Metro Delhi Border - Sector -32 NOIDA NOIDA
4 Gurgaon Extension of Delhi Metro ArjanGarh - Sushant Lok HUDA
5 Extension of Delhi Metro a) Extension of Rithala - Inderlok- Shahdara- GDA
to Ghaziabad Dilshad Garden line to Ghaziabad
New Bus Adda

b) Extension of Yamuna Bank -
Anand Vihar ISBT corridor to Vaishali
6 Bangalore Metro Line No 1 : Mysore Road to Baiyyappanahalli BMRCL
(East West Corridor)

Line No. 2 : Yeshwantpur to Jaya Nagar
( North South Corridor)

Yeshwantpura - Peenya Extension
North-South extension from
RV Road Terminal to Kankpura -
Ring Road junction
Total of 2 Lines
7 Mumbai Metro Master Plan Line No. 1 : MMRDA
Mumbai Metro Phase-I Versova - Andheri – Ghatkopar

Line No. 2 :
Colaba – Bandra - Charkop

Line No. 3 :
Bandra – Kurla -Mankhurd
Total of 3 Lines

Mumbai Metro Phase-I Revised (a) Revised alignment : Charkop - Bandra - Mankhurd
( In place of Line 2&3 above- Different Options)
(b) Revised Alignment :Colaba- Bandra MMRDA

(C)Revised Alignment : Charcop - Colaba

Total of 3 Lines Revised
8 Hyderabad Metro Line No 1 : Miyapur - Chaitanya Puri Govt. of Andhra Pradesh

Line No. 2 : Secunderabad – Falaknuma

Line No. 3.: Tarnaka – High-tech city- Nagole

Total of 3 Liness

Address:

Metro Bhawan
Fire Brigade Lane, Barakhamba Road,
New Delhi - 110001, India
Board No. - 011-23417910/11/12

DMRC Helpline nos.
155370
CISF Helpline nos.
155655
__________________
Answered By StudyChaCha Member
Reply With Quote
Reply


Reply to this Question / Ask Another Question
Your Username: Click here to log in

Message:
Options



All times are GMT +6. The time now is 04:32 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2023, vBulletin Solutions Inc.
Search Engine Friendly URLs by vBSEO 3.6.0 PL2

1 2 3 4 5 6 7 8